Practical Workbook 02 · Online edition

When the client
holds the constraints.

“The client won’t change it.” Have you asked the person who can?

Read here, add your notes or download the five-page A4 workbook. The online edition adapts to your screen and stays in light mode.

Your answers stay in this page and are not sent to us. Download your notes before leaving or refreshing; they are not saved automatically.

01 · Start with one constraint

Who can reconsider it?

Name one client-held constraint. Who can reconsider it, and what would they need to decide? Until you can answer, be careful about telling people that a choice is closed.

For the person who owns the decision

Your team needs a clear boundary, a route back to you and an answer in time to use it. Otherwise, they may promise too much or close down a choice you would have reconsidered.

What a useful escalation gives you

The impact on people, an option worth testing and the trade-off you need to decide. “The community won’t like it” gives you none of these.

Write the actual instruction or assumption, rather than “client requirements”.

02 · Find the basis

Find the basis. Find the authority.

Keep three things separate. Each calls for a different conversation.

A verified requirement

Find the exact approval condition, contract clause or technical limit. Record who checked it and who can advise on any permitted change.

A client instruction

Record who gave it, what it covers and who has authority to vary it. Treat a request for review as a question awaiting an answer, rather than permission to depart from the instruction.

An assumed preference

Trace “that’s how the client wants it” to a named person or record. Until it is checked, mark the boundary as unconfirmed.

Record the requirement, instruction or assumption and its reference.

Who can decide? Who must advise or approve? Who will take the question to them?

A client’s agreement may still need another approval. Keep current requirements in place until the authorised change is confirmed.

03 · Escalate

Take a decision back to the client.

Use this as one short escalation brief. Agree the route with your delivery lead and give the client decision-maker something specific to answer.

What are we instructed to do? What record supports it?

Who carries the impact, and for how long? Whose rights or cultural authority need direct engagement? Record evidence and uncertainty.

What could reduce the impact? What needs testing for safety, access, cost, programme and approvals?

Ask for a specific change or permission to test an option. State your recommendation and what happens if the current approach stays.

If an answer misses the deadline, agree the next escalation and tell people when they will hear again. Silence leaves the current boundary in place; it does not authorise a change.

04 · See it work

What a useful escalation looks like.

A fictional example: access during frontage works

The team is told to close a shopping-strip frontage in one continuous stage. “The client wants the shortest programme” becomes the explanation to traders.

The engagement lead checks with the delivery manager. Continuous closure is the client’s preferred sequence, not an approval requirement. The client project director can reconsider it, subject to technical and access checks.

Traders explain how the closure would interrupt deliveries and access. The team asks the client to fund a check of staged works, setting out the possible extra time and traffic-management cost.

The client funds the review. Checks confirm staged works are feasible, and the client authorises the additional cost and revised programme. Some short closures remain. The team explains those limits, agrees delivery windows and assigns the resulting commitments.

The record connects the original instruction, people’s experience, the option tested and the authorised change. A concern reached someone able to act on it.

What evidence or workable alternative would make our own escalation worth deciding?

05 · Tell people

Give people an honest answer.

Match the invitation to the authority you actually have. Make clear what can change and when people will hear back.

When a change is authorised

Explain the revised scope and invite input on choices still open. Name the decision-maker, the input deadline and the feedback date.

While the answer is pending

Explain what you have asked for, without promising a change.

“We have asked the client to reconsider ____. We cannot promise a change. You can help us understand ____. We will update you by ____, even if the decision is still pending.”

When the boundary stays

Explain who decided, what they considered and why the limit remains. Identify any genuine influence over delivery or impacts. Keep disagreement and unresolved concerns visible.

What is confirmed, what is pending, what can people influence and when will we update them?

Take your thinking with you.

Download a text copy of your answers to keep or share with your team. Nothing is submitted to the Ministry.

Next: Practical Workbook 03

Closing the loop when the answer is no.

Use and adapt the working pages for your own projects. Share the original with attribution. No resale or rebranding.

This is a planning aid, not evidence of support, and it won’t do the thinking for you.